Demolition of existing toilets, lobbies and corridor walls
Remodelling to form new internal corridors circulation areas, toilets and staff welfare facilities
Installation of bespoke kitchen units and fittings
Installation of new mechanical and electrical services
Installation of new specialist flooring and fittings
High quality decorations and french polishing
Project duration:
10 Weeks – 2018
Value:
£100,000
scope of works
Appointed by OutsourcedACC Ltd in January 2018, TCL was commissioned to provide new, high quality office welfare facilities and undertake the refurbishment of the main staircase and communal areas.
Throughout the project all works were executed in a dynamic, fully operational working environment.