Skip to main content

Case Study

Outsourced ACC – Internal Office Refurbishment


project details

Client:
Outsourced ACC Ltd
Overview:
  • Demolition of existing toilets, lobbies and corridor walls
  • Remodelling to form new internal corridors circulation areas, toilets and staff welfare facilities
  • Installation of bespoke kitchen units and fittings
  • Installation of new mechanical and electrical services
  • Installation of new specialist flooring and fittings
  • High quality decorations and french polishing
Project duration:
10 Weeks – 2018
Value:
£100,000

scope of works

Appointed by OutsourcedACC Ltd in January 2018, TCL was commissioned to provide new, high quality office welfare facilities and undertake the refurbishment of the main staircase and communal areas.

Throughout the project all works were executed in a dynamic, fully operational working environment.

Download PDF