Demolition of existing lobbies, remodelling to form new internal corridors, circulation areas, office areas, toilets and staff welfare facilities
Provision of new front entrance fire doors and frames & Fire stopping
Asbestos removal
Application of fire retardant paint finish (Tor Coating) to communal lobbies, staircases and all associated fire escape areas
Provision of smoke/heat detectors
Replacement of chute hoppers and refuse store doors
Project duration:
16 Weeks – 2012
Value:
£60,000
scope of works
Netley House is a 60’s built 6 storey, concrete frame residential tower block comprising of 27 dwellings, situated in the heart of Camberwell.
As part of London Borough of Southwark’s Fire Precautionary Programme, TCL were appointed in July 2012 to undertake a number of fire prevention improvement works. Untaken with resident’s in-situ.