Robert Owen Nursery School – Educational Refurbishment
project details
Client:
Royal Borough of Greenwich
Overview:
Demolition of existing classrooms and ancillary rooms.
Construction of 7 new classrooms, toilets and kitchens
Re-modelling of offices and staff facilities
Construction of a new office facility
M&E design & installation
HVAC design and installation
Incorporation of new doors and windows in existing elevations
Project duration:
8 weeks + 1 week mobilisation – 2017
Value:
£525,000
scope of works
Following a fast-track competitive tender process TCL were appointed in June 2017 with a 1-week mobilisation period in which to plan and commence works. The contract commenced with the refurbishment of a single classroom whilst the remainder of the school was open with the remainder of the works comprising the strip-out and full refurbishment of 6 x classrooms, toilets, kitchens and administration facilities as well as a new-build office area, all completed during the summer holiday.