Dilkes Academy Primary School – Educational Refurbishment
project details
Client:
Dilkes Academy Primary School
Overview:
New build extension to accommodate increased teaching facilities
Creation of new entrance foyer, reception area and staff room facilities
New bespoke entrance canopy
Disabled access works
New lighting and electrical installation
Suspended ceiling
New kitchen installation
Proprietary flooring
New window and door fenestration
Project duration:
12 Weeks (2016)
Value:
£185,000
scope of works
As part of the Dilkes Academy expansion programme, TCL were appointed in June 2016 to undertake the building of a new extension and internal remodelling to accommodate a new entrance foyer, reception and staff room facilities.
The project had to be delivered within a tight timeframe during the summer break ready for the school reopening in the first week of the new term.